Free Planning tool

Depot charging calculator

Use this free depot charging calculator to estimate how much energy your fleet needs each night, how many AC and DC chargers to install and what size they should be, and how much grid capacity your depot needs, with and without load management.

Row of electric vans plugged into post-mounted AC chargers at a depot

Calculator

Size your depot charging

Your fleet and site

Start with the example figures, then replace them with your own. Results update as you type.

Overnight charging
miles
kWh
hours
kW
kW
Vehicles needing a daytime top-up
kWh
min
hours
kW
ResultsSee results ↓

Your results

Estimates to guide planning, not a design.

–kWh from the grid per vehicle per day
–average kW per vehicle overnight
–AC chargers
–DC chargers
–kWh per night for the fleet
–kW capacity needed with load management
Discuss your results
Assumptions and disclaimer. Results are planning estimates, not a design. Energy per vehicle includes a 20% allowance for winter weather and battery ageing and a 10% allowance for charging losses. Average power is energy divided by the charging window. Charger sizes are the smallest standard rating (7, 11 or 22 kW AC; 50, 100, 150 or 350 kW DC) that meets the need, never above what the vehicle can accept, because a larger charger adds cost without charging faster. DC charging slows as the battery fills, so real top-ups take longer than a flat-rate calculation suggests. Capacity with load management adds 25% headroom to the fleet's average load, a rule of thumb to check against your half-hourly meter data. DC chargers are shared on a rota, allowing 10 minutes per changeover. Check every vehicle model's specification and your site's electrical design with a qualified engineer.

How to use it

Getting reliable results

Get the inputs right


Use a busy day, not the average

Use real energy figures from telematics or trials

Allow for late returns and early starts

Take charge acceptance from each vehicle specification

Reading the results


One AC charger per vehicle, sized to what it needs

Load management sizes the grid to the average, not the peak

DC chargers only for vehicles that cannot wait

Amber messages show where to look harder

Questions

Frequently asked questions

How accurate is the depot charging calculator?


It gives planning estimates from the figures you enter. A full design should use half-hourly meter data, vehicle schedules and each model's charging limits.

Why size chargers to charge acceptance?


A vehicle charges no faster than its own limit, so a charger larger than it can accept adds cost without saving time.

Why does load management reduce the capacity needed?


It shares the available power between chargers, so the site never needs every charger running at full power at once.

What if my site does not have enough capacity?


Options include a flexible connection, battery storage and phasing the rollout, while the full connection is arranged.

What is charge acceptance?


It is the maximum power a vehicle can take: on AC, the rating of its on-board charger; on DC, its maximum DC charging power. Both are in the vehicle specification.

Does the calculator allow for charging losses and winter?


Yes. It adds 20% for winter weather and battery ageing and 10% for charging losses to the energy each vehicle needs.

Talk to us about your depot

Send us your results and we will tell you plainly what your depot needs: chargers, power, storage and the order to do it in.